Why you should avoid linking summary tasks.
Linking summary tasks in MS Project has some negative consequences for project planning. Though MS Project allows summary tasks to be linked as a predecessor or successor, you may want to avoid this altogether for some of the reasons listed below.


  • can produce errors in logic
  • can artificially extend the project plan
  • can cause circular logic warning messages
  • when you link a summary task and detail task you are defining a dependency between the deliverable and tasks required to produce that deliverable, which does not make sense. This alone is reason enough to deter one from inserting summary tasks dependencies.
  • makes the effort to check if the network of dependencies is complete more difficult
  • the critical path is also more difficult to map out
  • not recommended by the Project Management Institute’s PMBOK

Links between summaries are also not advisable according to MS best practice guidelines.